Gwynt y Môr

Fault Management

BACKGROUND

A €2 billion project, Gwynt y Môr consists of 160 turbines in Liverpool Bay, off the North Wales coast. 

 

EDS'S INVOLVEMENT

 

EDS demonstrated their unparalleled reputation as experts in the offshore wind industry by performing 2 subsea cable fault repairs.

From the first fault & emergency call, EDS were able to mobilise and deploy a team to carry out pre-location fault finding within just 24 hours.  EDS experts turnkeyed the entire solution from locating and excavating to repairing, testing and re-energising the cables.  The 132kV subsea joints were completed in less than 48hrs potentially saving thousands in lost generation and availability. 

 Their contribution to this project means that EDS have had a critical part to play in the repair all 3 major cable failures this year.

 

 